Storing and Preserving MV Motors Before Commissioning

16.11.26 10:33 AM

In short: large motors often wait months, sometimes years, between delivery and commissioning on Saudi projects. In that time dust, humidity swings, condensation and vibration from nearby work can damage windings and bearings before the motor ever runs. A preservation routine (dry, covered storage, energised space heaters, periodic insulation resistance tests, regular shaft rotation and correct bearing care) protects the motor and the warranty and avoids failures at start-up. BTGC supplies WEG MV and HV motors and supports preservation, inspection and pre-commissioning checks.

WEG medium voltage motor

On large projects, motors arrive early with the driven equipment packages and then sit on laydown yards, in partly built substations or on installed skids while construction continues. Coastal sites see high humidity at night and temperatures above 45 °C by day; inland sites see dust storms. Both are hard on insulation and bearings that are not running.

What goes wrong in storage

RiskCauseResult
Low insulation resistanceMoisture absorbed by windings during humid nights, condensationFailed IR or PI test at commissioning, or a fault at first energisation
False brinellingVibration from nearby equipment while the shaft is stationaryMarked bearing races and noisy bearings from day one
Bearing corrosionCondensation in bearing housings, degraded grease or oilPitting and early bearing failure
Dust and sand ingressOpen terminal boxes, missing covers, outdoor storageContaminated windings, blocked cooling passages
Sleeve bearing damageOil drained for shipping not refilled, or the shaft turned dryWiped bearing surfaces

A practical preservation routine

  • Store indoors or under cover, on a level base, away from vibration sources, with terminal boxes and openings sealed.

  • Energise the space heaters continuously in storage and after installation until the motor runs, to keep the windings above the dew point.

  • Measure insulation resistance and polarisation index on arrival and at regular intervals, typically monthly, and record them with the winding temperature.

  • Rotate the shaft by hand every few weeks to a new position, to redistribute lubricant and change the loaded points in rolling bearings; refit the transport lock before moving the motor.

  • Look after bearings and lubricant: keep sleeve bearing housings at the storage oil level the maker specifies, and regrease rolling bearings as the storage instructions require.

  • Protect machined surfaces such as shaft ends and feet with preservative, and inspect it periodically.

WEG high voltage industrial motor

Insulation resistance targets

IEEE 43 gives the recommended minimum insulation resistance and polarisation index for rotating machines. For form-wound MV windings, the recommended minimum insulation resistance corrected to 40 °C is 100 megohms, and the recommended minimum polarisation index for Class F insulation is 2.0. A falling trend in storage matters more than any single reading: it shows moisture getting in, and the winding should be dried with heaters or a controlled low-voltage current before the motor is energised.

Before the first start

  • Review the storage records with the commissioning team and the manufacturer.

  • Repeat IR and PI tests, and dry the winding if the results are low.

  • Inspect bearings, renew grease or oil if storage has exceeded the maker's limit, and check end float.

  • Remove the transport lock, check alignment and soft foot, and confirm cooling paths are clear.

  • Run uncoupled first where the procedure allows, with vibration and temperature monitoring.

WEG from BTGC

BTGC is the WEG partner in Saudi Arabia for medium and high voltage motors and MV drives. The BTGC service center in Jubail, a WEG approved service center, carries out site inspections, winding drying, bearing work and pre-commissioning tests. See also preventing stator winding failure and bearing currents in VFD-driven motors.

Questions buyers ask

How long can an MV motor be stored? With proper preservation, many months to years; beyond the maker's storage limit, bearings and lubricants need inspection or renewal before start-up.

Should heaters stay on after installation? Yes, until the motor is in regular service, and during long stops afterwards.

Can BTGC check motors stored on our site? Yes. BTGC can inspect, test and report on stored motors and carry out drying or bearing work where needed.

Contact the BTGC power division

Email power@btc-ksa.com or call +966 13 856 0528. Branches: Dammam, Jubail and Yanbu. Request a quote.