In short: valves are one of the largest work packages in any refinery turnaround: hundreds or thousands of valves are inspected, repaired, tested or replaced in a few weeks. Good planning starts many months before: building the scope from inspection and leak data, ordering spare parts and replacement valves early, booking workshop capacity, and agreeing test and documentation requirements. A well-planned valve package shortens the turnaround and prevents leaks at start-up. BTGC supplies Pacific refinery valves and spares, with testing and repair at its Jubail service center.

Refineries and petrochemical complexes in the Kingdom run major turnarounds every few years. Valve delays are a common cause of turnaround overruns.
Building the valve scope
List valves with known leakage, passing seats, stem leaks or operating problems from the last run.
Add valves due by inspection interval, regulatory requirement or risk-based inspection.
Include safety and relief valves due for testing.
Mark critical valves on the turnaround critical path.
Decide repair or replace for each valve using condition, age and cost.
Spares and long-lead items
| Item | Planning point |
|---|---|
| Replacement valves in special materials | Order many months ahead |
| Trims, seats and pressure seal rings | Order from inspection findings and history |
| Gaskets, packing and bolting | Standardise and stock in advance |
| Actuators and accessories | Check compatibility and lead times |

Execution and quality
Book workshop and test bench capacity before the turnaround starts.
Tag and track every valve from removal to reinstallation.
Test to API 598 or owner requirements and record results.
Torque bolting to procedure and record values.
Hand over complete records for each valve after start-up.
Pacific Valves from BTGC
Pacific Valves is the Crane ChemPharma and Energy brand for cast steel gate, globe and check valves in demanding refinery services. BTGC is the Pacific Valves partner in Saudi Arabia through Crane, with valve testing and repair at the Jubail service center. See also pressure seal valve repair, safety valve testing and the oil and gas sector page.
Questions buyers ask
How early should turnaround valve spares be ordered? As early as possible; special materials and large valves can take many months.
Repair or replace? Repair when the body is sound and parts are available; replace when damage, age or cost of repair makes it uneconomic.
Can BTGC support turnaround valve work? Yes, with spares, replacement valves and testing at the Jubail service center.
Contact the BTGC valve team
Email valves@btc-ksa.com or call +966 13 856 0528. Branches: Dammam, Jubail and Yanbu. Request a quote.