In short: a transformer can be damaged during transport, storage or installation, and wiring or protection mistakes can cause trouble on first energising. Commissioning tests check oil quality, insulation, windings, ratio and vector group, and confirm that protection devices and controls work. They also record a baseline, such as SFRA and DGA results, that future tests are compared with. BTGC supplies Arabian Transformers Company transformers and supports their commissioning.

New substations, industrial plants, solar farms and giga-projects in the Kingdom commission large numbers of transformers. A careful first energising prevents early failures and disputes.
Typical commissioning tests
| Test | Checks |
|---|---|
| Visual and mechanical | Damage, leaks, earthing, clearances, accessories |
| Oil tests | Breakdown voltage, moisture and baseline DGA |
| Insulation resistance and PI | Overall insulation condition |
| Winding resistance | Connections and tap changer contacts |
| Turns ratio and vector group | Correct ratio on all taps and correct phase shift |
| SFRA | Baseline for future checks of winding movement |
| Protection and controls | Buchholz, pressure relief, temperature devices, CTs and alarms |
Before energising
Check transport shock recorder results for large units.
Confirm oil levels and that valves to radiators and conservator are open.
Vent air from radiators, bushings and Buchholz relay.
Check tap position and control settings.
Confirm protection settings and trip tests.

First energising and after
Energise with protection in service and observe for noise, heating and alarms.
Hold a soak period before loading where specified.
Take oil samples after a set period for DGA comparison; see oil testing and DGA.
Record all results in a commissioning report.
Plan routine tests; see transformer protection.
Arabian Transformers from BTGC
Arabian Transformers Company (ATC) manufactures distribution and power transformers, compact substations and package units in the Kingdom. BTGC is the ATC partner in Saudi Arabia. See also dry-type vs oil-immersed transformers, the electrical power systems page and the power and utilities sector page.
Questions buyers ask
Why record an SFRA baseline? Later tests can be compared with it to detect winding movement after faults or transport.
Do repaired transformers need commissioning tests? Yes, the same checks apply after major repairs.
Does BTGC support transformer commissioning? Yes, with ATC transformers and testing coordination.
Contact the BTGC power division
Email power@btc-ksa.com or call +966 13 856 0528. Branches: Dammam, Jubail and Yanbu. Request a quote.