Transformer Commissioning Tests: What to Check Before Energising

18.11.26 09:02 AM

In short: a transformer can be damaged during transport, storage or installation, and wiring or protection mistakes can cause trouble on first energising. Commissioning tests check oil quality, insulation, windings, ratio and vector group, and confirm that protection devices and controls work. They also record a baseline, such as SFRA and DGA results, that future tests are compared with. BTGC supplies Arabian Transformers Company transformers and supports their commissioning.

Arabian Transformers distribution transformer

New substations, industrial plants, solar farms and giga-projects in the Kingdom commission large numbers of transformers. A careful first energising prevents early failures and disputes.

Typical commissioning tests

TestChecks
Visual and mechanicalDamage, leaks, earthing, clearances, accessories
Oil testsBreakdown voltage, moisture and baseline DGA
Insulation resistance and PIOverall insulation condition
Winding resistanceConnections and tap changer contacts
Turns ratio and vector groupCorrect ratio on all taps and correct phase shift
SFRABaseline for future checks of winding movement
Protection and controlsBuchholz, pressure relief, temperature devices, CTs and alarms

Before energising

  • Check transport shock recorder results for large units.

  • Confirm oil levels and that valves to radiators and conservator are open.

  • Vent air from radiators, bushings and Buchholz relay.

  • Check tap position and control settings.

  • Confirm protection settings and trip tests.

Utility plant

First energising and after

  • Energise with protection in service and observe for noise, heating and alarms.

  • Hold a soak period before loading where specified.

  • Take oil samples after a set period for DGA comparison; see oil testing and DGA.

  • Record all results in a commissioning report.

  • Plan routine tests; see transformer protection.

Arabian Transformers from BTGC

Arabian Transformers Company (ATC) manufactures distribution and power transformers, compact substations and package units in the Kingdom. BTGC is the ATC partner in Saudi Arabia. See also dry-type vs oil-immersed transformers, the electrical power systems page and the power and utilities sector page.

Questions buyers ask

Why record an SFRA baseline? Later tests can be compared with it to detect winding movement after faults or transport.

Do repaired transformers need commissioning tests? Yes, the same checks apply after major repairs.

Does BTGC support transformer commissioning? Yes, with ATC transformers and testing coordination.

Contact the BTGC power division

Email power@btc-ksa.com or call +966 13 856 0528. Branches: Dammam, Jubail and Yanbu. Request a quote.